Plants open · Mallavarappadu & GundlapalliMon – Sat · 9:30 AM – 6:00 PM
Global Readymix& Global Metals
తెలుగు
HomeConcreteAggregatesPlantsOn-siteAboutContact

How much concrete do I need? A simple volume guide

Ready-mix concrete is ordered and billed by volume — in cubic metres (m³) — not by bags. Getting the number right means you avoid both a short pour and paying for concrete you do not use. Here is the simple way to work it out.

The basic formula

Concrete volume is just length × width × thickness, with every dimension in metres. The answer comes out in cubic metres (m³):

Volume (m³) = Length (m) × Width (m) × Thickness (m)

The only thing to watch is units. Slab and footing thickness is usually given in millimetres, so convert it first — divide by 1000. A 150 mm slab is 0.15 m thick.

Worked examples

A floor slab 4 m long, 3 m wide and 150 mm thick:

4 × 3 × 0.15 = 1.8 m³

A column 230 × 230 mm and 3 m tall:

0.23 × 0.23 × 3 = 0.159 m³ — round up to about 0.16 m³ each

For repeated elements — say ten identical columns — work out one and multiply by the count. For footings, calculate one footing and multiply by the number of footings.

Always add a wastage allowance

Real pours never use the exact theoretical volume. Spillage, uneven sub-grade, formwork bulge, and pump priming all consume a little extra. Add a wastage allowance on top of your calculated figure:

  • Flat slabs and large pours: about 3–5%
  • Columns, beams, and footings with rough ground: about 5–8%
  • Small or awkward pours: up to 10%

For the 1.8 m³ slab above, a 5% allowance takes the order to roughly 1.9 m³.

Converting to transit-mixer loads

Our transit mixers carry up to 6 m³ each. Dividing your order quantity by 6 tells you roughly how many loads will arrive — useful for planning access, labour, and pour sequence.

1.9 m³ ÷ 6 ≈ 1 transit-mixer load

Larger pours that need several loads back-to-back are worth scheduling with us in advance so dispatch from the Mallavarappadu and Gundlapalli plants is continuous and the concrete stays workable.

Skip the maths — use the calculator

Our free concrete calculator does all of this for you. Pick the element type, enter the dimensions, set a wastage percentage, and it returns the order quantity in m³, the number of mixer loads, and a suggested grade. Send that figure to us as a starting point — our engineer confirms the volume, pumping, and site access on a free site visit before issuing your quote.

FAQ

Common questions

Is concrete sold by the bag or by volume?
Ready-mix concrete is sold by volume in cubic metres (m³). Bags are only relevant for hand-mixing small quantities on site; for any slab, beam, column, or footing of a reasonable size, ordering ready-mix by the m³ is more economical and consistent.
How many bags of cement are in 1 m³ of concrete?
It depends on the grade, but a typical M20 mix uses roughly 6 bags (about 300 kg) of cement per cubic metre — the IS 456 minimum for that grade — along with the appropriate sand and aggregate. With ready-mix you do not buy cement separately — the batch slip records the exact mix for the load you receive.
How much extra concrete should I order for wastage?
Add about 5% for most slabs and a little more — up to 8–10% — for columns, footings, or pours over rough ground. It is cheaper to allow a small surplus than to run short mid-pour and create a cold joint.

Ready to order?
Estimate the volume, then get a quote